Anglian Water Works in Folksworth

FROM AWA:

I wanted to get in touch to update you on our upcoming project in Folksworth. We’re still planning to start construction work on 27 June 2022 with our site compound set up starting on the 13 June.

 

Our team will work in 200metres sections of the road at a time, digging a trench, inserting sections of the pipe, joining them, and then backfilling and reinstating the section of road before moving to the next. To keep our team and the public safe we need to implement phases of road closures:

 

Location Start date End date
Townsend Way to Manor Road – Road Closure 27 June 2022 29 July 2022
Manor Road to Morborne Road – Road Closure 18 July 2022 12 August 2022
Morborne Road to A1 roundabout – Road Closure 01 August 2022 23 September 2022

There will be no through traffic and a clearly sign posted diversion route will be in place for road users which has been agreed with the local highway authority and an expert traffic management company.

 

Please note, the road closure dates overlap so we can progress to the next section without needing to pause work and may change depending on progression of work. Access will always be maintained for residents who live within our closure from one direction or the other.

 